[1]张 胜,何文超,黎永索,等.小净距隧道洞口段地表下沉分段曲线拟合研究[J].湖南城市学院学报(自然科学版),2019,28(5):1-5.[doi:10.3969/j.issn.1672-7304.2019.05.0001]
 ZHANG Sheng,HE Wenchao,LI Yongsuo,et al.Study on Piecewise Curve Fitting of Surface Settlement at Neighborhood Tunnel in the Portal Section[J].,2019,28(5):1-5.[doi:10.3969/j.issn.1672-7304.2019.05.0001]
点击复制

小净距隧道洞口段地表下沉分段曲线拟合研究()
分享到:

《湖南城市学院学报(自然科学版)》[ISSN:1006-6977/CN:61-1281/TN]

卷:
28
期数:
2019年5期
页码:
1-5
栏目:
土木工程
出版日期:
2019-09-20

文章信息/Info

Title:
Study on Piecewise Curve Fitting of Surface Settlement at Neighborhood Tunnel in the Portal Section
文章编号:
1672–7304(2019)05–0001–05
作者:
张 胜1何文超2黎永索1蔡 鑫1刘志斌1
1. 湖南城市学院 土木工程学院,湖南 益阳 413000;2. 长沙理工大学 土木工程学院,长沙 410114
Author(s):
ZHANG Sheng1 HE Wenchao2 LI Yongsuo1 CAI Xin1 LIU Zhibin1
1. School of Civil Engineering, Hunan City University, Yiyang, Hunan 413000, China; 2. School of Civil Engineering, Changsha University of Science & Technology, Changsha, Hunan 410114, China
关键词:
小净距隧道洞口段地表下沉分段曲线拟合
Keywords:
neighborhood tunnel portal section surface settlement piecewise curve fitting
分类号:
U45
DOI:
10.3969/j.issn.1672-7304.2019.05.0001
文献标志码:
A
摘要:
针对基于最小二乘法的曲线拟合方法无法考虑小净距隧道先、后洞相互影响的施工特点,根据隧道先、后洞不同步开挖对洞口段地表下沉规律的影响,提出一种新的预测地表下沉的分段曲线拟合方法,并对隧道施工现场洞口段地表下沉量测数据进行分段曲线拟合分析﹒结果表明:采用分段曲线拟合法能较好反映地表下沉随先行洞与后行洞掌子面向前掘进的变形规律并可预测最终下沉量,避免了多项式函数无法预测最终下沉量以及指数与对数函数拟合精度偏低等问题;隧道先、后洞由不同步施工开挖引起的地表下沉量沉降槽曲线并不对称,最大地表下沉量偏向后行洞﹒
Abstract:
The construction characteristics of mutual influence in the first tunnel and the second tunnel are not considered in curve fitting method based on the least squares. A new piecewise curve fitting method is proposed to predict surface settlement according to the influence of unsynchronized excavation of the first and second tunnels. The piecewise curve fitting is used to analyze on-site monitoring measurement data of surface settlement at tunnel portal section. The results show that using the piecewise curve fitting method can better reflect the deformation law of surface settlement along with the excavation of the first tunnel and the second tunnel, and can forecast the final settlement. At the same time, the problems, such as the failure of polynomial function fitting to predict the final settlement and the low accuracy of exponential and logarithmic function fitting are avoided. The curve of surface settlement caused by unsynchronized excavation in two tunnels is asymmetry, and the maximum surface settlement happens to the second tunnel.

备注/Memo

备注/Memo:
收稿日期:2019-03-27 基金项目:国家自然科学基金资助项目(51608183,51678226);湖南省自然科学基金资助项目(2018JJ3022);湖南城市学院土木工程国家级实验教学示范中心大学生创新实验计划项目(2018) 第一作者简介:张胜(1984-),男,湖南安化人,讲师,博士,主要从事隧道与地下工程研究.E-mail: zhangsheng0403311@163.com
更新日期/Last Update: 2019-10-24